Slab casting day: quantities, the night-before checks, the pour and the dates after

A roof slab gets one day. Once the concrete starts going in, you can't stop to send for more cement, a second vibrator or the cube moulds. So most of the work happens in the two days before the pour, and the engineer's inspection of the steel is part of it. This page goes from the drawings to the strip dates on your calendar.

By Bulan Sarkar · Updated

14 m³a typical 1,000 sq ft roof slab with its beams (our worked example)
112 bagsof cement for 14 m³ of M20 (CPWD DAR item 4.1.2, 8.0 per m³)
2 minminimum mixing time per batch in a mixer (IS 456 cl. 10.3.1)
1.5 mthe most concrete should fall freely as it is placed (IS 456 cl. 13.2)
6 cubes2 samples of 3 for 6 to 15 m³ of one grade (IS 456 cl. 15.2.2)
Quick Answer

Take the concrete volume and grade of the slab and beams from the drawings. A 1,000 sq ft roof with its beams is often about 14 m³, which is 112 bags of cement for M20 at CPWD's 8.0 bags per m³ (117 with wastage), and 2 cube samples of 3 cubes each under IS 456 cl. 15.2.2. Two or three days ahead, get the full material lot on site. The day before, have the engineer check the steel, the cover blocks and the shuttering. On the day, start early, run a mechanical mixer (at least 2 minutes a batch, cl. 10.3.1), keep a spare vibrator, and pour continuously up to the joints the engineer has marked. Start curing once the surface has set: 7 days of wet curing for OPC, 10 for PPC (cl. 13.5.1). Then write the strip and prop dates on a calendar, and leave the final call on them to the engineer.

Source: IS 456:2000 Plain and Reinforced Concrete, Code of Practice: cl. 10.1.2 and 10.1.3 (inspect each step before the next covers it; pour cards and inspection records), 10.2.6, 10.3 and 10.3.1 (mechanical mixer, 2 minutes), 11.1 to 11.3.2 (formwork and stripping times), 12.2 to 12.3.2 (cover blocks, spacers at 1 m, cover tolerance), 13.1 to 13.6 (transport, placing, 1.5 m free fall, vibration, joints, curing, supervision) and 15.2 (cube sampling), checked Oct 2026.

The decision: run slab casting day yourself?

Do it yourself

Yes, if you are building on a labour-only or part-material contract and you are the one ordering material and hiring the mixer. This page gives you the quantities, the order of the day, the cube count and the dates to write down. You run the checklist; the engineer gives the go-ahead.

Skip the full plan

On a turnkey contract the builder runs the day. Skip the ordering, but still be there: check the cube count and labels, take photos of the steel before it is covered, and get the cast date and the strip dates in writing.

Get help

The slab thickness, the steel in it, the concrete grade, where a construction joint may go and when the props can come out are for a licensed structural engineer. Have the engineer (or the site engineer they send) inspect the steel, the cover and the shuttering and say yes before the first batch is mixed. Ask before adding water, changing the cement or the mix, or switching to ready-mix.

The steps, in order

1Volume and grade2Material on site3Day-beforechecks4Crew andmachines5The pour6Curing and dates7Record
  1. Get the volume and grade from the drawings

    Have ready:the structural drawings for the slab and beamsthe concrete grade the engineer has specified (M20, M25…)

    Ask the engineer for the concrete volume of the slab and the beams cast with it, and the grade. If the drawings only give sizes, run each member through the RCC calculator. For the worked example on this page: a 1,000 sq ft roof is 92.9 m², which at 125 mm thick is 11.6 m³ of slab, plus 2.4 m³ of beams below it, 14 m³ in all.

    Then turn the volume into material with the concrete calculator. CPWD's analysis of rates puts M20 at 8.0 bags of cement per m³, so 14 m³ needs 112 bags; our calculator adds 3% wastage and says 117. The same calculator gives the sand and aggregate in cft and brass.

    Open the RCC Slab, Beam and Column Calculator

  2. Get the slab-day lot on site two or three days ahead

    Have ready:the bag, sand and aggregate figures from step 1a dry place for the cement, off the floor

    All the cement, sand and aggregate for the pour should be on site two or three days before, checked at the truck and written in the delivery log. If material runs short in the middle of a slab, the concrete already placed keeps setting while you wait for the next truck.

    Count the bags the evening before. The material order for one floor covers the delivery checks for each material.

    Open the Concrete Calculator

  3. The day before: steel, cover and shuttering checked

    Have ready:the engineer or site engineer, booked for the inspectiona phone to photograph the steel before it is covered

    IS 456 asks for every step that the next one will cover to be inspected as the work goes on (cl. 10.1.2), and calls supervision of the steel before it is covered extremely important (cl. 13.6). So the steel inspection happens before the pour, not on the morning of it. Walk the slab with the engineer and check:

    • Cover blocks under the bottom bars, the same thickness as the nominal cover on the drawing, and spacers or chairs no more than 1 m apart (cl. 12.3.2). On a 93 m² slab that is about one block per square metre, roughly 90 to 120 of them, more under the beams. The cover can come out up to 10 mm more than the nominal figure, never less. Our cover blocks and chairs guide has the counts and the chair height.
    • The top steel sitting on its chairs, not pressed down onto the bottom bars by people walking on it.
    • The shuttering clean of sawdust, chippings and wire bits, oiled with release agent but not the steel (cl. 11.2), and tight enough that slurry won't run out of the gaps (cl. 11.1).
    • Pipes and boxes for wiring and plumbing in place and tied, so nobody cuts the slab later.

    Photograph the steel, room by room. Those photos are the only record of what is inside the slab.

  4. Plan the people, machines and the order of the pour

    Have ready:a mechanical mixer and a needle vibrator, plus a spare vibratorcube moulds, a slump cone if the engineer wants slump checks, lights and water

    IS 456 cl. 10.3 asks for concrete to be mixed in a mechanical mixer, and cl. 10.3.1 for at least 2 minutes of mixing a batch. Batching goes by the 50 kg bag (Table 9 sets nominal mixes per bag), so 112 bags means about 112 batches, which is 224 minutes, close to 4 hours, of mixing alone before any loading, carrying or placing. That is why slab day starts at first light.

    Ask the engineer where the pour starts, which way it moves and where a construction joint may go if the day runs out (cl. 13.4 leaves the joint positions to the designer). Keep a spare vibrator and fuel for the mixer on site; the code wants the concrete compacted with mechanical vibrators (cl. 13.3.1), and a breakdown halfway leaves you with an unplanned joint.

    Open the Concrete Calculator

  5. Pour without stopping, and take the cubes as you go

    Have ready:6 cube moulds for 14 m³ (more for a bigger pour)a marker and the cube record sheet

    The concrete is placed as close as it can be to where it stays, compacted before it starts to set, and not dropped more than about 1.5 m (cl. 13.2). Under-vibration leaves honeycombs; over-vibration and very wet mixes are both called harmful (cl. 13.3.1). No water gets added to make a batch flow better unless the engineer agrees: cl. 10.2.6 bars changes to the set proportions without tests.

    Take the cube samples from batches spread over the whole pour, not all from the first ones (cl. 15.2.1). For 6 to 15 m³ of one grade, IS 456 cl. 15.2.2 asks for 2 samples of 3 cubes each. Label every cube with the date and the batch, and fill in the record sheet before the day ends. The cube test guide has the full table and the record sheet.

  6. Start curing, then write the dates on a calendar

    Have ready:water and a hose or tanker booked for the curing dayshessian for beam sides and edges, bricks and mortar for ponding bunds

    Once the surface has set, keep the concrete continuously wet: at least 7 days for OPC, at least 10 for PPC, PSC or any blended cement, and the code recommends stretching blended cement to 14 (cl. 13.5.1). For a slab cast on Monday 2 November 2026, that is wet until 9 November for OPC, 12 November for PPC, 16 November for the recommended 14 days.

    IS 456 cl. 11.3.1 gives minimum times before the formwork and props come out, for OPC above 15 °C with good curing: slab soffit shuttering 3 days (props refixed at once), slab props 7 days up to a 4.5 m span, beam soffits 7 days, beam props 14 days up to a 6 m span. Write them on the calendar as the earliest possible dates. The engineer decides the actual day. The curing and props guide covers both in full.

  7. File the slab-day record

    Have ready:the kit's slab-day sheetthe bills, delivery log and steel photos

    Before you leave site, fill in the slab-day sheet: cast date and start and finish times, grade and volume, bags used against bags on site, the batches each cube sample came from, any stop and where it happened, and the curing and strip dates. IS 456 lists pour cards and site inspection records among the papers a job should keep (cl. 10.1.3). When the 28-day cube report comes back, it goes into the same file.

Slab casting day, from the drawings to the strip dates1 volume and grade from the drawings; 2 material on site two or three days ahead; 3 the day before, the engineer checks steel, cover blocks and shuttering; 4 slab day, mixer and vibrator, a continuous pour with cubes taken through it; 5 curing starts once the surface sets and the strip dates go on a calendar.1Volume and grade from the drawings14 m³ of M20 = 112 bags (CPWD), 117 with wastage2Slab-day lot on site two or three days aheadbags counted the evening before3Day before: steel, cover blocks, shutteringengineer says go; photos of the steel4Slab day: one continuous pour2 min a batch, spare vibrator, cubes spread over the pour5Curing and the strip dates7 days wet (OPC) or 10 (PPC); props on the engineer's say
Slab casting day, from the drawings to the strip dates. Each step is checked before the next one covers it, as IS 456 cl. 10.1.2 asks. The engineer's go-ahead after the steel inspection is the gate between the day-before checks and the first batch.
Earliest dates for a slab cast on Monday 2 November 2026Slab soffit shuttering 3 days, 5 November. Slab props up to 4.5 m span 7 days, 9 November. Beam soffit 7 days, 9 November. Wet curing for OPC 7 days, 9 November. Wet curing for PPC 10 days, 12 November. Beam props up to 6 m span 14 days, 16 November.Slab soffit shuttering (props refixed)3 days, 5 NovSlab props, span up to 4.5 m7 days, 9 NovBeam soffit shuttering7 days, 9 NovWet curing, OPC7 days, 9 NovWet curing, PPC or PSC10 days, 12 NovBeam props, span up to 6 m14 days, 16 Nov
Earliest dates for a slab cast on Monday 2 November 2026. IS 456 cl. 11.3.1 (OPC, 15 °C or warmer, good curing) and cl. 13.5.1. Day counts from the cast date: 3 days to 5 Nov, 7 to 9 Nov, 10 to 12 Nov, 14 to 16 Nov. These are minimums for the engineer to confirm, not dates to strip on.
Cubes to cast by pour volume (one grade)5 cubic metres: 3 cubes. 14 cubic metres: 6 cubes. 25 cubic metres: 9 cubes. 45 cubic metres: 12 cubes. 60 cubic metres: 15 cubes.5 m³ (1 sample)3 cubes14 m³ (2 samples)6 cubes25 m³ (3 samples)9 cubes45 m³ (4 samples)12 cubes60 m³ (5 samples)15 cubes
Cubes to cast by pour volume (one grade). IS 456 cl. 15.2.2: 1 sample for 1 to 5 m³, 2 for 6 to 15, 3 for 16 to 30, 4 for 31 to 50, then one more for each further 50 m³ or part of it, and at least one sample a shift. Each sample is 3 cubes.

What goes wrong

The cement runs out with a third of the slab leftThe lot was worked out from a rough figure or was due the same morning. Take the volume from the drawings, get the whole lot on site two or three days early, and count the bags the evening before.
The mixer or the only vibrator breaks at middayThe pour stops wherever it is, not at a joint the engineer chose. Keep a spare vibrator and fuel on site, and agree beforehand where the pour may stop if it has to.
Honeycombs show under the beams when the shuttering comes offThe concrete wasn't vibrated well around the bars, or slurry ran out of gaps in the shuttering. Show it to the engineer before anyone plasters over it.
The bottom bars sit on the shuttering in placesCover blocks were missing, broken or too far apart, or people walked on the mesh. Blocks go no more than 1 m apart, and walking planks go down before the pour.
Water was added at the slab to make the concrete flowThat changes the mix the engineer specified and weakens the concrete. Ask for the slump the engineer wants and keep the water to the batch figure.
All six cubes came from the first two batchesThe test then says little about the rest of the slab. Spread the samples over the whole pour and write the batch on each cube.

Variants: what changes the steps

Ready-mix concrete and a pump

The plant mixes and the pump places, so step 4 becomes booking trucks at a steady interval and checking each delivery ticket for grade, volume and the time it left the plant. Keep the tickets with the slab-day sheet. Cube sampling for plant concrete can be agreed between supplier and buyer (IS 456 cl. 15.2.2 note), so settle who casts the cubes before the day.

Site-mixed with a lift or head pans

The mixer sits at ground level and the concrete goes up by a hoist or by hand. Count the carrying crew against the mixer's output so batches don't wait. The 1.5 m free-fall limit applies where it is tipped onto the slab.

Hot, dry weather

Pour early in the day or in the evening and keep the surface from drying out. IS 456 cl. 13.1.1 asks for deep containers so less water evaporates on the way, and cl. 13.5.1 raises the minimum curing to 10 days for any cement in hot, dry weather.

Rain likely on the day

Keep polythene sheets and a few people ready to cover fresh concrete, and decide with the engineer beforehand whether a heavy forecast means moving the date. A finished slab under a sudden shower needs covering, not more water.

Tips and tricks

  • Book the engineer's steel inspection for the afternoon before the pour, not the morning of it. If something needs fixing, the bar bender has the evening to do it.
  • Lay walking planks across the top steel before the crew arrives. It keeps the top bars on their chairs.
  • Write the batch count on a board by the mixer. When bags and batches stop matching, you find out at once, not at the end of the day.
  • Keep the cube moulds oiled and the 16 mm tamping bar on site the day before, so sampling doesn't wait on someone's errand.
  • Ask the curing helper to sign a sheet three times a day. A slab that dries out on the second afternoon doesn't show it until much later.
  • Take the photos of the steel with a tape in the frame for the cover blocks and the bar spacing.

What we would do

We would book the engineer's inspection for the afternoon before, start mixing at first light with a spare vibrator on site, and pour without stopping up to a joint the engineer has already named. We'd take the cubes from early, middle and late batches, write the curing and strip dates on the wall of the site shed the same evening, and wait for the engineer to say when the props come out. If the slab is more than about 20 m³, we'd ask the engineer whether ready-mix and a pump make more sense than a site mixer.

Free kit page

Print the working copy

Slab casting day sheet, from the Slab Casting Day Kit. One A4 page with tick boxes and blanks; it prints in black and white.

Print the working copy

  • 1. From the drawings
  • 2. Day before
  • 3. The pour
  • 4. Dates (earliest; engineer confirms)

Frequently asked questions

How many cement bags do I need for a 1,000 sq ft roof slab?
It depends on the thickness and the beams, so take the volume from the drawings. As an example, a 125 mm slab over 92.9 m² is 11.6 m³, and with 2.4 m³ of beams that makes 14 m³. At CPWD's 8.0 bags per m³ for M20 that is 112 bags, or 117 with 3% wastage in our concrete calculator.
What should be checked before slab casting?
The steel against the drawings, cover blocks at the nominal cover and no more than 1 m apart, the top steel on its chairs, clean and tight shuttering, pipes and boxes tied in, and all the material on site. The engineer should inspect the steel and say yes before the first batch.
How many cubes should be taken during slab casting?
IS 456 cl. 15.2.2 sets samples by volume of each grade: 1 sample for 1 to 5 m³, 2 for 6 to 15, 3 for 16 to 30 and 4 for 31 to 50. Each sample is 3 cubes, so a 14 m³ slab needs 6 cubes, taken from batches spread over the pour.
How long does it take to cast a house roof slab?
With a site mixer, plan the full day. Each batch needs at least 2 minutes of mixing (IS 456 cl. 10.3.1), and at one bag a batch, 112 bags is close to 4 hours of mixing alone, before loading, carrying, placing and finishing.
Can the slab casting stop halfway and continue the next day?
Only at a construction joint the engineer has placed. IS 456 cl. 13.4 calls joints a common source of weakness and asks for concreting to run continuously up to them. If a stop can't be avoided, call the engineer before restarting.
When can the slab shuttering be removed?
IS 456 cl. 11.3.1 gives minimums for OPC at 15 °C or warmer with good curing: 3 days for slab soffit shuttering with the props refixed, 7 days for slab props up to a 4.5 m span, 14 days beyond that. Blended cements and cold weather need longer, and the engineer gives the actual date.

The source we built this on

IS 456:2000 Plain and Reinforced Concrete, Code of Practice: cl. 10.1.2 and 10.1.3 (inspect each step before the next covers it; pour cards and inspection records), 10.2.6, 10.3 and 10.3.1 (mechanical mixer, 2 minutes), 11.1 to 11.3.2 (formwork and stripping times), 12.2 to 12.3.2 (cover blocks, spacers at 1 m, cover tolerance), 13.1 to 13.6 (transport, placing, 1.5 m free fall, vibration, joints, curing, supervision) and 15.2 (cube sampling). Checked Oct 2026.

Read 18 Oct 2026 from the page images (printed pp. 24 to 29). The bag figure uses the CPWD Delhi Analysis of Rates 2023 item 4.1.2 coefficient behind our cost model (checked Jul 2026). The 14 m³ slab, the bags-per-batch count and the cover-block count are our worked examples, not figures from the code.

This plan covers quantities, ordering, the order of the day and records. The slab's design, its steel, the grade and mix, any joint and the stripping of props are for a licensed structural engineer. Nobody stands under a slab while it is being cast or while its props are being moved.