Guide · 3 worked examples

Curing a concrete slab: how many days, how to keep it wet, and how long the props stay

IS 456 asks for 7 days of wet curing with ordinary Portland cement and at least 10 with PPC or slag cement. Here is the rule, a curing calendar, the water a ponded slab takes, and the earliest prop dates to plan your shuttering hire around.

By Bulan Sarkar · Updated

Quick Answer

IS 456:2000 clause 13.5.1 says the exposed concrete must be kept continuously wet, by ponding or by wet sacking, for at least 7 days from the day it was placed when the cement is ordinary Portland (OPC), and at least 10 days when it is a blended cement such as PPC or PSC, or contains fly ash or slag. In dry, hot weather the minimum is 10 days for any cement, and for blended cements the code recommends stretching it to 14 days. So a PPC slab cast on 2 November stays wet until at least 12 November, better 16 November.

Source: IS 456:2000 Plain and Reinforced Concrete, Code of Practice (with Amendments 1 and 2), clauses 11.3 and 13.5, checked Oct 2026.

7 daysminimum wet curing with OPC (IS 456 cl. 13.5.1)
10 daysminimum with PPC, PSC or fly ash, or in hot dry weather
14 dayswhat the code recommends for blended cements
7 / 14 daysearliest slab props out, span up to / over 4.5 m (OPC, 15 °C+)

How many days: read the cement bag first

The number of curing days depends on the cement, not on how strong the slab looks on day 3. IS 456:2000 clause 13.5.1 (as amended) gives three minimums for wet curing, counted from the date the concrete is placed:

Minimum wet curing period (IS 456:2000 cl. 13.5.1)
Cement or conditionMinimumWhat the code adds
Ordinary Portland cement (OPC 43, OPC 53)7 daysKept continuously damp or wet
Blended cement (PPC, PSC) or a mix with fly ash or slag10 daysRecommended: extend to 14 days
Any concrete exposed to dry and hot weather10 daysNot less than 10 days

The cement type is printed on the bag: PPC carries IS 1489, PSC carries IS 455 and OPC carries IS 269. Check one bag from the lot before the pour and write the type in your slab-day notes. If the slab is ready-mixed concrete, the delivery challan or the mix design names the cement and any fly ash or slag; ask for it.

Hot weather has its own standard. IS 7861 (Part 1):1975 calls concreting hot weather work when the air is above 40 °C or the concrete goes in above 40 °C, and clause 8.2 again sets curing at not less than 10 days. It also changes the pour: when temperatures are critical, it suggests casting in the evening or at night.

No clause asks for 28 days of curing. Twenty-eight days is the age at which the test cubes are crushed, which is a separate job covered in our cube test guide.

Minimum days of wet curingOPC in normal weather: 7 days. Any cement in hot dry weather: 10 days. PPC or PSC, or fly ash or slag in the mix: 10 days minimum. Blended cement, recommended: 14 days.OPC, normal weather7 daysAny cement, dry and hot weather10 daysPPC or PSC, or fly ash or slag in the mix10 days minimumBlended cement, what the code recommends14 days
Minimum days of wet curing. From IS 456:2000 cl. 13.5.1 (as amended). Days are counted from the date the concrete is placed.

How to keep the slab wet

Clause 13.5.1 allows two methods: ponding, or covering the concrete with sacking, canvas, hessian or something similar that is kept constantly wet. The aim is the same either way. The surface must never dry out between checks, because concrete that dries and gets wet again cracks at the surface.

  1. In hot weather, as soon as the surface is finished, lay wet (not dripping) gunny bags or hessian on it. IS 7861 cl. 8.2 asks for this straight after finishing, so the slab doesn't lose water while it hardens.
  2. Start the moist curing proper once the surface can take water without damage. IS 7861 puts that at roughly 12 hours after mixing in hot weather.
  3. For ponding, build low bunds of lean mortar on the slab to make bays, and keep water standing in them. This works well on a flat roof slab and is easy to check from the stairs.
  4. On beams, sloping slabs, sunshades and columns, wrap the concrete in hessian and wet it often enough that it stays soaked. IS 7861 cl. 8.2.1 says not to count on the shuttering to keep moisture in during hot weather.
  5. Clause 13.5.2 allows an approved curing compound in place of water only with the engineer's permission, sprayed on every exposed face once the concrete has set. Polythene sheet laid close on the surface is also allowed as a barrier.
  6. On the last day, leave the wet covers in place until they dry by themselves (IS 7861 cl. 8.2.3), so the slab doesn't dry fast in the wind.
A PPC slab's curing, from the pour to the last day1 pour and finish; 2 wet hessian straight away; 3 about 12 hours later start ponding or soaked sacking; 4 check morning, afternoon and evening; 5 day 10 is the minimum for PPC; 6 day 14 is the recommended end, leave covers to dry off.1Pour and finish the surfaceWrite the date and the cement type down2Wet hessian or gunny bags on topWet, not dripping, straight after finishing3About 12 hours: start ponding or soaked sackingBunds on the flat slab, hessian on beams and edges4Check it three times a dayTop up the pond, re-wet the sacks5Day 10: the minimum for PPC or PSCDay 7 if the bag says OPC6Day 14: the recommended endLet the last covers dry off on their own
A PPC slab's curing, from the pour to the last day. Timings from IS 456:2000 cl. 13.5 and IS 7861 (Part 1) cl. 8.2. The 12-hour mark is the code's rough figure for hot weather.

Props and shuttering: the dates to plan your hire around

Most house owners hire shuttering plates and steel props by the day, so the number of days the props stay under the slab is a real cost. IS 456 clause 11.3 sets the rule: formwork comes off only when the concrete has reached at least twice the stress it will carry at that moment. Clause 11.3.1 then lists stripping periods that meet that rule in normal conditions, which means ordinary Portland cement, air not below 15 °C, and proper curing:

Minimum period before striking formwork, OPC at 15 °C or above (IS 456:2000 cl. 11.3.1)
FormworkMinimum
Vertical faces of columns, walls and beams16 to 24 hours
Slab soffit shuttering (props refixed at once)3 days
Beam soffit shuttering (props refixed at once)7 days
Props under slabs spanning up to 4.5 m7 days
Props under slabs spanning over 4.5 m14 days
Props under beams and arches spanning up to 6 m14 days
Props under beams and arches spanning over 6 m21 days

Two things in that clause matter for a house. First, the table is for OPC. For other cements and lower temperatures the code says the periods "may be suitably modified", so a PPC slab, or one poured on a cold winter day, needs the engineer's own dates. Second, "props refixed at once" means the plates can go back to the hirer early, but props stay. Clause 11.3.2 asks for enough props, of the right size and spacing, to carry the slab and any load on it while the next work goes on. Use these dates to plan the hire. The engineer decides on the day when anything comes out.

Keep a curing sheet

Curing is the one slab-day job that nobody can check later. A crack or a low cube result three weeks on sends everyone back to ask whether the slab was kept wet, and a sheet answers that. One line a day is enough:

Curing sheet columns
ColumnExample
Day and dateDay 4, 6 Nov 2026
Cement on the bagPPC (IS 1489), so 10 days minimum
Morning check7:30, pond full, sacks wet
Afternoon check14:00, east bay dry, refilled
Evening check18:30, all bays full
Water usedAbout 900 litres from the sump
Checked byName

Write the end dates on the sheet on day one: the minimum day, the recommended day, and the earliest prop dates from the table above. Then nobody has to work them out when the labour wants to move on.

Worked examples

1. Curing calendar for a PPC roof slab

  • Slab cast on Monday 2 November 2026 with PPC from the bag (IS 1489)
  • IS 456 cl. 13.5.1: blended cement, at least 10 days
  • 2 Nov + 10 days = Thursday 12 November, the minimum last day of wet curing
  • The code recommends 14 days for blended cement: Monday 16 November
  • Had the bag said OPC: 7 days, so Monday 9 November

Result: Keep the slab wet until at least 12 November and plan for 16 November. Put both dates on the curing sheet on the day of the pour.

2. How long to hire the props

  • OPC concrete, November, days above 15 °C, curing done properly
  • Room spans up to 4.2 m, one room 4.8 m; longest beam 5.4 m
  • Slab soffit plates: earliest day 3, with props refixed at once (cl. 11.3.1 b)
  • Props under the 4.2 m rooms: 7 days; under the 4.8 m room: 14 days (over 4.5 m)
  • Props under the beams (up to 6 m): 14 days

Result: Budget the props for at least 14 days and the plates for at least 3. With PPC or in a cold month, the table no longer applies as printed, so get the engineer's dates before you sign the hire.

3. Water for ponding a 1,000 sq ft slab

  • Slab area: 1,000 sq ft × 0.0929 = 92.9 m²
  • A pond 25 mm deep: 92.9 × 0.025 = 2.32 m³ = about 2,320 litres for the first fill
  • Each 1 mm the water drops: 92.9 × 0.001 m³ = about 93 litres to top up
  • If you measure a 10 mm drop overnight: about 930 litres to refill
  • Measure the drop on day 2 with a steel rule in one bay, then plan the sump or tanker

Result: About 2,300 litres to fill a 25 mm pond on 1,000 sq ft, then roughly 93 litres for every millimetre lost. Check the sump has that much before the pour day.

Tips and tricks

  • Count the days from the pour date, not from the day the ponding started. Clause 13.5.1 counts from the date the concrete was placed.
  • Name one person for curing and agree their pay for the full 10 or 14 days before the pour.
  • Build the mortar bunds for the ponds on the evening of the pour or the next morning, so the bays are ready when the surface can take standing water.
  • Don't spray cold water straight onto a slab that has been sitting in the hot sun. IS 7861 cl. 8.2.3 warns that curing water much cooler than the concrete can crack it.
  • Wrap the beam sides and the slab edges in hessian too. The pond only reaches the top surface, and the edges dry first.
  • Write PPC or OPC, and the curing end date, in chalk on a column at the stair landing where everyone walks past.

What we would do

We'd check the cement on the bag before the pour and plan for 14 days of wet curing if it is PPC or PSC, which covers both the minimum and the code's recommendation. We'd pond the roof slab in bays, wrap beams and edges in hessian, and pay one person to check it morning, afternoon and evening, with a sheet they sign. For the props, we'd ask the engineer for the stripping dates before signing the hire, and budget at least 14 days for props under the beams and any room wider than 4.5 m. The slab casting day checklist puts this into the order of the whole day, with a sheet to print.

Frequently asked questions

How many days should a concrete slab be cured?
IS 456:2000 cl. 13.5.1 asks for at least 7 days of continuous wet curing with ordinary Portland cement and at least 10 days with blended cements such as PPC or PSC, or with fly ash or slag in the mix. In dry, hot weather it is at least 10 days for any cement, and for blended cements the code recommends 14.
Does a slab need 28 days of curing?
No clause in IS 456 asks for 28 days. The minimums are 7 and 10 days, with 14 recommended for blended cement. Twenty-eight days is the age at which test cubes are crushed to check the concrete's strength.
How many days of curing for PPC cement?
At least 10 days of wet curing from the day the concrete is placed, and the code recommends 14. IS 456 cl. 13.5 notes that keeping the water in matters most for concrete containing slag or fly ash, which is what PPC and PSC are made with.
When can slab shuttering be removed?
IS 456 cl. 11.3.1 lists 3 days for slab soffit shuttering with the props refixed at once, 7 days for props under slabs spanning up to 4.5 m and 14 days over 4.5 m. Those figures assume OPC, air at 15 °C or more and proper curing. With other cements or in cold weather the periods change, and the engineer decides.
Can I use a curing compound instead of water?
Only with the engineer's permission, under IS 456 cl. 13.5.2. The compound goes on every exposed surface as soon as the concrete has set. Polythene sheet laid closely on the concrete is also allowed as a barrier against evaporation.
When should curing start after casting a slab?
In hot weather, IS 7861 (Part 1) cl. 8.2 asks for wet, not dripping, gunny bags or hessian straight after the surface is finished, and moist curing proper from about 12 hours after mixing, once the surface can take it without damage.

Sources and date checked

This guide covers curing days, curing methods, record keeping and planning the prop hire. When the shuttering and props come out, the slab's design, and what to do about a crack or a low cube result are for your structural engineer to decide.