River sand runs ₹60–110 per cft, M-sand ₹45–75/cft and 20 mm aggregate ₹35–55/cft delivered (as of Jul 2026). One tonne of loose dry sand occupies roughly 22–24 cft, one brass is exactly 100 cft, and one m³ is 35.31 cft, so a 10-tonne sand truck carries about 2.2–2.4 brass. Enter your quantity in any unit below to convert it and see the dated cost band.
Rates checked Oct 2026. Source: CPWD Delhi Analysis of Rates 2023, Civil Vol. I — coarse sand (zone III, natural) applied at ₹1,450/cum in CPWD's own concrete/mortar analyses (verified firsthand).
Part of the system: Material order for one floor, Slab casting day. Steps, checks and a free printable page.
Guide: Measure a sand or aggregate truck.
Runs entirely in your browser — nothing you enter is uploaded.
Volume units (cft, m³, brass) convert exactly. Weight ↔ volume is a band, not a number, because loose bulk density varies with moisture and gradation. The density bands used are published in the assumptions and every price is dated in the rates table.
Every number below is a range with a date — material prices in India move quickly, so always check the "as of" month before relying on a figure.
| Item | Rate / value | As of | Note |
|---|---|---|---|
| River sand | ₹60–110 / cft | Oct 2026 | Checked on 23 Oct 2026: no newer schedule or dated dealer price found, so the band carries forward. Re-anchored 2026-07-25: the three content farms (HouseYog, Civiconcepts, Varna Homes) that used to back this band are struck; it now rests on two government schedules read firsthand — but be clear about what they anchor. CPWD DAR 2023 applies coarse sand (zone III, natural) at ₹1,450/cum throughout its own concrete and mortar rate analyses = ₹41/cft ex-GST, ₹43/cft incl. 5% GST (a stray basic-rate index line at ₹285/cum is an anomalous layout artifact, not the applied rate; the '₹1,450 = spirit/air-compressor' reading is a coincidental-value misread — the operative applied rate is ₹1,450). Maharashtra PWD SSR 2022-23 (p.541) gives natural/VSI/artificial sand ₹1,670/cum = ₹47/cft, crushed ₹1,200/cum = ₹34/cft, screened natural (plaster) ₹1,781/cum. So the government evidence pins an EX-GST, EX-CARRIAGE, AT-SOURCE rate of ~₹41–47/cft (~₹43–50 incl. GST at yard) — and that is ALL it pins. The ₹60 floor is that yard rate plus a minimum ~₹15/cft lead (matching delivered Delhi ≈ ₹50–65); it is lowered from ₹70, which came only from the now-struck per-tonne blog quotes. The ₹110 ceiling is deliberately NOT re-sourced — no primary or retail anchor exists above ₹70 now — and the whole upper half is extrapolation (source rate + heavy lead + retail margin + documented 30–50% mining-ban and monsoon spikes). That is exactly why this is medium, not high, and why the carriage bridge from source to delivered is a fitted, unverified step, disclosed as such. Do not cite the schedules as proof of the delivered band; they anchor only the floor. South metros (Bangalore/Chennai/Hyderabad) sit at the ceiling and above, North plains and near-river Maharashtra at or below the floor; transport adds ₹15–40/cft. Unit exactness is the classic sand failure: confirm cft vs brass (1 brass = 100 cft = 2.83 cum) vs tonne vs truckload and whether transport is in the quote; 1 cum = 35.3147 cft. Density (resolved, unchanged): 22–24 cft/t (1,470–1,600 kg/m³) from IS 2386 Pt III, classical tables and trade 1 brass ≈ 4.5 t — do NOT cite IS 383 for density, it grades aggregate, it does not weigh it. GST 5% (natural sand HSN 2505), asserted from the standing schedule and NOT re-verified against a CBIC notification this pass — flagged. State sand portals (Telangana TGMDC, AP) are JS booking apps that expose no static notified rate. |
| M-sand (manufactured) | ₹45–75 / cft | Oct 2026 | Checked on 23 Oct 2026: no newer schedule or dated dealer price found, so the band carries forward. Re-anchored 2026-07-25; content farms (HouseYog, Civiconcepts, Varna Homes) struck. ₹45–75/cft delivered retail incl. 5% GST, the South- and West-India default. Government anchor — Maharashtra PWD SSR 2022-23 (ex-GST, ex-carriage): crushed sand ₹1,200/cum (₹34/cft) and VSI/artificial ₹1,670/cum (₹47/cft) against natural screened ₹1,781/cum; +5% GST and ₹15–40/cft carriage bridge these to the delivered band, and the SSR's own contractor crushed-sand work-item (incl. labour, ≤5 mm) at ₹1,859/cum = ₹53/cft corroborates the upper zone. Cheaper than river sand: standard crushed M-sand runs ~28–33% below natural sand in the SSR itself, and the gap widens in the South where river sand carries mining-ban scarcity premiums — but note VSI premium-grade M-sand is priced level with natural sand, so the saving is a standard-grade, same-market comparison, not universal. Delhi CPWD DAR 2023 carries no quarry-M-sand line, only recycled-RCA manufactured sand at ₹1,400/cum, which confirms M-sand as a South/West material. Consistent gradation, no monsoon or mining-ban seasonality. Same honest limit as the river entry: the government schedules anchor only the ex-GST at-yard floor (~₹36 crushed); the ₹75 ceiling and the delivered span above the floor rest on a modelled carriage bridge, not observed Southern retail — hence medium, and the anchor is Western/Delhi and 2022-23 vintage. GST 5% (HSN 2517), asserted from the standing schedule, not re-verified against CBIC this pass. |
| Coarse aggregate (20 mm) | ₹35–55 / cft | Oct 2026 | Checked on 23 Oct 2026: Material99 still lists 20 mm aggregate at ₹34–55/cft. Delivered retail; ex-supplier ₹700–900/tonne (~₹32–41/cft; 1 cft ≈ 45 kg). Long lead distances push delivered price toward ₹68/cft. 10 mm runs ₹2–5/cft above 20 mm. Official anchor (verified 2026-07): CPWD DAR 2023 20 mm single-size ₹1,425/cum = ₹40.3/cft ex-GST ex-carriage (Delhi, Apr 2023) — mid-band once carriage and GST are added; lifted to high. Primary-minerals WPI +12% YoY (Apr 2026): extraction costs are rising. |
Cement bags, sand, aggregate and water for any slab, by grade, with the formula shown.
Bricks, mortar cement and sand for any wall, worked from real brick sizes.
How much will your house cost to build? Dated rates, formula shown, honest ranges.
How many bags of cement a job needs, for any concrete mix or mortar, with the working shown.
How much TMT steel does your house need? Thumb-rule quantity and dated cost.
Your house budget split into the 13 lines CPWD uses to track building costs, with material, labour and a printable plan.