Repaint your home before Diwali: paint, putty, primer and the days it takes

Diwali falls on Sunday, 8 November 2026. Work out the litres from the paint's own datasheet, book the painter for the right dates, and every room is dry before the diyas come out.

By Bulan Sarkar · Updated

130 to 150sq ft per litre over two coats (Tractor)
250 to 270sq ft per litre for one coat (Tractor)
4 hoursbetween coats of paint, at 25 °C
8 Nov 2026Diwali (central holiday list)
Quick Answer

A 2BHK of about 750 sq ft has roughly 2,625 sq ft of walls and ceilings (floor area × 3.5). An interior emulsion such as Asian Paints Tractor covers 130 to 150 sq ft per litre over two coats, according to its datasheet, so you need about 18 to 20 litres. Add 10% and buy a 20 L and a 4 L pack. Putty goes only on damaged patches, and primer goes on the patches and on walls changing from a dark colour to a light one. Allow about three working days for each batch of rooms, because each coat needs about 4 hours before the next. To finish by 1 November, start by 21 October, the day after Dussehra.

Source: Asian Paints Tractor Emulsion technical data sheet (India): coverage 250 to 270 sq ft/L one coat and 130 to 150 two coats, application steps, 4 h recoat, 28 days curing for new plaster, thinned paint used within 24 hours, checked Oct 2026.

The decision: repaint yourself, or with your usual painter, this month?

Do it yourself

Yes, if the walls are sound and dry, the paint is only dull or marked, and you are keeping a similar colour. This page covers that whole job, from measuring to the last touch-up.

Skip the full plan

Skip the full repaint if only one or two walls look tired. Repaint those walls from corner to corner (a patch in the middle of a wall shows) and leave the rest for next year.

Get help

Get help first for damp patches, paint peeling off in sheets, white salt deposits that keep coming back, or cracks wider than a fingernail. Those come from water or the structure, and paint will not fix them, so have a contractor or engineer find the cause. Also wait if the plaster is new: Asian Paints asks for 28 days of curing, and IS 2395 says to leave new cement plaster unpainted for as long as possible.

The steps, in order

1Fix the dates2Measure rooms3Mark repairs4Read the tin5Work out litres6Buy the packs7Prepare8Putty, prime9Two coats10Touch up, record
  1. Fix the dates and work backwards from Diwali

    Have ready:a calendaryour painter's phone number

    Diwali is on Sunday, 8 November. Keep the last week for cleaning and putting furniture back, so the painting ends by 1 November. A 2BHK done in two batches of rooms takes about six working days, so starting on 21 October, the day after Dussehra (20 October), leaves a few spare days. Painters get booked up in late October, so fix the dates now and get them in writing.

  2. Measure each room

    Have ready:a measuring tapethe room sheet from this page

    Either measure each wall (length × height, minus doors and windows) or take the floor area × 3.5 for walls plus ceiling. A 12 × 10 ft bedroom has a 120 sq ft floor, so about 420 sq ft to paint. Give each room its own line on the sheet.

    Open the Paint Calculator

  3. Walk the walls and mark the repairs

    Have ready:a pencila torchmasking tape to flag spots

    At night, hold a torch flat against the wall so dents, cracks and old drips throw a shadow. Circle each one. Flag damp or salty patches separately, because they go to the "get help" list and not to the painter. Then estimate the patched area as a share of each room; write 10% if you are unsure and adjust after the walk.

  4. Read the coverage off the paint's datasheet

    Have ready:the product name, or a photo of the tin's label

    Datasheets print two lines, and mixing them up is the usual reason people buy double. Tractor Emulsion: 250 to 270 sq ft per litre for one coat, 130 to 150 over two coats. Royale Luxury: 270 to 310 for one coat, 140 to 160 over two. Berger Bison: 130 to 150 over two coats. Two coats is the normal repaint; Berger's sheet says two for the same colour and three for fresh painting.

    Open the Paint Calculator

  5. Work out the paint, putty and primer

    Have ready:the room totals from step 2the patch share from step 3

    Paint: total area ÷ the low end of the two-coat figure, plus 10% (or enter the one-coat figure and 2 coats in the paint calculator). Putty: patched area ÷ 38 sq ft per kg for one coat, or ÷ 24 for two coats (Asian Paints Acrylic Wall Putty prints 38 to 44 and 24 to 35). Primer: patched area plus any wall going from dark to light, ÷ 215 sq ft per litre (Decoprime water-thinnable primer: 215 to 270 for one coat).

    Open the Paint Calculator

  6. Buy in pack sizes, from one batch

    Have ready:the shade codethe litres, kg and pack sizes

    Paint comes in 1, 4, 10 and 20 L packs and putty in 1, 5, 10, 20 and 35 kg. Large packs cost far less per litre: Tractor's MRP is ₹4,180 for 20 L (₹209 a litre) against ₹258 for 1 L, and dealers usually sell below MRP. Ask for the same batch number on every tin of one shade, and check it before you leave the shop.

  7. Empty, cover and sand the room

    Have ready:plastic sheetmasking tape180-grit sandpaper

    Move the furniture to the middle and cover it. Tape over switchboards and sockets without opening them. Sand the old paint lightly with 180-grit paper, which is the first step in the Tractor datasheet, and wipe the dust off. Run a palm over the wall: if dust comes away, wipe again.

  8. Putty and spot-prime the patches (day 1)

    Have ready:acrylic wall puttya putty knifewater-thinnable primer

    Fill the marked spots with putty. A second coat can go on after 4 to 6 hours. Sand it smooth once dry, then prime the patched areas. The datasheet order is sand, primer, putty, sand, primer, sand, then the paint, and the primer needs 4 to 6 hours before the next step. Run a palm over each patch; you should not feel an edge.

  9. Two coats of paint (days 2 and 3)

    Have ready:the paint, thinned as the datasheet saysrollers and a tray

    Thin the paint as the datasheet says: 40 to 45% water for brush or roller on Tractor and Royale. Mix only what you will use that day, because thinned paint is good for 24 hours. Leave about 4 hours between coats (3 to 4 for Royale) at 25 °C, longer when it is cold or humid, and do not paint below 10 °C. Paint the ceiling first, then each wall from corner to corner.

    Open the Paint Calculator

  10. Inspect, touch up and record

    Have ready:the room sheetthe leftover tins

    Walk the rooms in daylight and touch up from the same batch. Write the product, shade code, batch number and date on the room sheet, and keep a labelled litre of leftover paint for next year's marks. Then move to the next batch of rooms.

One coat or two: what a litre coversRoyale, one coat270 to 310Tractor, one coat250 to 270Royale, two coats140 to 160Tractor, two coats130 to 150Bison, two coats130 to 150
One coat or two: what a litre covers. Sq ft per litre from the Asian Paints Tractor Emulsion and Royale Luxury datasheets and the Berger Bison data sheet (bar at the middle of each printed range). The two-coat figure is about half the one-coat figure. Use one of them, never both multiplied together.
Litres to buy for two coats, by home size500 sq ft flat (1,750 sq ft)14.8 L750 sq ft flat (2,625 sq ft)22.2 L1,100 sq ft flat (3,850 sq ft)32.6 L
Litres to buy for two coats, by home size. Floor area × 3.5 for walls and ceiling (the sq ft to paint, in brackets), ÷ 130 sq ft per litre (the low end of Tractor's two-coat figure), plus 10%. Round up to the packs on the shelf.

What goes wrong

You run out halfway along a wallThe litres came from a one-coat figure, or the 10% was skipped. A tin from another batch can leave a visible band, so stop at a corner and buy enough the first time.
You buy twice the paint you needThe two-coat figure (130 to 150) was treated as a one-coat figure and multiplied by two coats. Check which line of the datasheet you used.
The new paint blisters or flakes within weeksDust or grease was left on the wall, or a damp wall was painted. IS 2395 says to paint only once the excess moisture has dried out.
White powder comes back through the paintThat is efflorescence, salts carried out by water. IS 2395 says to dry-brush it and not wash it off, and the water source has to be found. Leave that wall out and get help.
The patches show as dull spotsThey were not primed after the putty, so they soak up paint differently from the rest of the wall. Spot-prime every patch.
The job runs into Diwali weekThe painter started late or the coats did not get their drying time. Book early and work in batches of rooms instead of the whole house at once.

Variants: what changes the steps

Same colour, sound walls

Most homes. Sand, putty and prime the patches, then two coats. This is the three-day batch above.

Dark to light, or a new colour scheme

Prime the whole wall first, then two coats. Berger's sheet calls for three coats on a fresh surface, so budget a third coat when you are covering a very dark old colour.

New plaster in an extension or a replastered room

Wait at least 28 days (Asian Paints), and longer if you can: IS 2395 says new cement plaster should stay unpainted as long as possible and new brickwork for at least three months. If that room cannot wait, leave it for after the festival.

Rented flat

Ask the owner first, keep to the same colour, and photograph every wall before and after for the deposit.

Tips and tricks

  • Check walls at night with a torch held flat against the surface. Dents and old drips show up far better than in daylight.
  • Photograph each tin's label on the day you buy it: shade code, batch number and the coverage line. Next year's touch-up then matches.
  • Pull the masking tape off while the last coat is still slightly soft. Once the paint hardens, the tape can lift it.
  • Thin only the paint you will use that day. Thinned emulsion is good for 24 hours, and the rest goes to waste.
  • Paint the ceiling before the walls, so any drips land on surfaces that are still to be painted.

What we would do

For a 2BHK last painted four or five years ago, staying in the same colour, we would book the painter this week for 21 October, measure the rooms tonight on the sheet below, and buy a 20 L and a 4 L pack of one batch, a 10 kg bag of acrylic putty (one coat on about 380 sq ft of patches) and a 4 L can of water-thinnable primer (about 860 sq ft for one coat). We would do the bedrooms first and the living room and kitchen second. Any damp wall stays out of this year's job and gets looked at after the festival, since paint on a damp wall has to be redone once the cause is fixed.

Free kit page

Print the working copy

Repaint room sheet: rooms, litres and days, from the Repaint Planner. One A4 page with tick boxes and blanks; it prints in black and white.

Print the working copy

  • The job
  • Rooms
  • Packs to buy
  • Each batch of rooms
  • Leave out of this job

Frequently asked questions

How many litres of paint do I need for a 2BHK?
About 18 to 20 litres for two coats on roughly 2,625 sq ft of walls and ceilings (a 750 sq ft flat × 3.5), using the 130 to 150 sq ft per litre two-coat figure on the Tractor and Bison datasheets. Add 10% and buy a 20 L and a 4 L pack.
Is 130 sq ft per litre for one coat or two?
On the Asian Paints Tractor and Berger Bison datasheets, 130 to 150 sq ft per litre is the figure over two coats. One coat of Tractor covers 250 to 270 sq ft per litre. Read your own tin carefully, because mixing the two up is the usual reason for buying double.
Do I need putty and primer for a repaint?
Only where the wall is damaged or the colour changes a lot. Putty goes on dents and cracks, and primer on the patches and on any wall going from dark to light. Sound walls in the same colour need a light sanding and two coats.
How long should I wait between coats?
About 4 hours between coats of Tractor Emulsion and 3 to 4 hours for Royale, at 25 °C and 50% humidity, and 4 to 6 hours between coats of putty, according to the Asian Paints datasheets. Wait longer in cold or humid weather.
How long after new plaster can I paint?
Asian Paints asks for 28 days of curing. IS 2395, the Indian code for painting plastered and masonry surfaces, says new cement plaster should stay unpainted as long as possible and new brickwork for at least three months.
When should I start painting to finish before Diwali 2026?
Diwali is on 8 November 2026. A 2BHK takes about six working days in two batches of rooms, so starting by 21 October leaves time to finish by 1 November and keep the last week for cleaning.

The source we built this on

Asian Paints Tractor Emulsion technical data sheet (India): coverage 250 to 270 sq ft/L one coat and 130 to 150 two coats, application steps, 4 h recoat, 28 days curing for new plaster, thinned paint used within 24 hours. Checked Oct 2026.

Also checked on 7 Oct 2026: Asian Paints Royale Luxury, Decoprime water-thinnable primer and Acrylic Wall Putty sheets; the Tractor product page (pack MRPs); the Berger Bison data sheet; IS 2395 (Part 1):1994 cl. 5.2.2, 7.2, 7.4 and Annex C-3.1; and the central government holiday list for 2026 (Dussehra 20 Oct, Diwali 8 Nov). Prices are maker's MRPs on that date.

Use a stable step-ladder, keep the windows open while painting and drying, and keep children and pets out of the rooms in use. Tape over switches and sockets; do not open the switchboard. Damp, cracks and seepage go to a contractor or a licensed engineer.